Construction News at West
September 2, 2025
As construction picks up again on campus, we will provide notification of significant activity here and other useful information.
Occurring between September 2 - 19
Foundation Excavation
- May experience hauling and concrete trucks on route
- Rebar delivery with crane – Sept 8 - 9
- Rebar installation – Sept 8 - 12
- Concrete pour – Boom pump – Sept 15 - 19
Project Description |
Scheduled Start |
Anticipated Completion |
Notes |
Pant Facilities and Shops Replacement |
2025, Q2 * |
2027, Q2 ** |
|
Heldman Sequence 1 |
2025, Q4 ** |
2026, Q3** |
Site demolition |
Football Field - Storm Water Implementation |
2025, Q3 * |
2026, Q1 ** |
Storm Water Implementation |
Northwest Drainage Area - Storm Water Implementation |
2025, Q3 * |
2026, Q1 ** |
Storm Water Implementation |
|
|
|
|
* = Actual Date **= Anticipated